State Highway 2 1800mm culvert line
July 28, 2025
In early 2025, Nicholls and Uttinger Civil were engaged to install a stormwater pipeline upgrade under State Highway 2, between Tauranga and Katikati.Works included installing a new 1800mm diameter culvert and a new 600mm diameter culvert underneath State Highway, plus assoc...
Te Anga Road Slip Repairs
April 30, 2025
In April 2025, Nicholls and Uttinger Civil were selected by Waitomo District Council to carry out repairs of two slip sites, near Te Anga.The works involved tree clearing, bulk earthworks, construction of a 5m high magnumstone block retaining wall, stormwater pipe upgrades, ...
Port Waikato slip repairs
December 11, 2024
In late 2024, Nicholls and Uttinger Civil was engaged by Waikato District Council to undertake critical repairs on two significant road slips near Port Waikato, which were impacting access to the local community.The project involved a range of complex civil works, including:...
Taumatatotara West Road slip repair
January 15, 2024
October - November 2023
Restoring access to the local community was of vital importance for the Waitomo District Council when a 3,800m3 slip cut off access during an adverse weather event late last year.Our skilled team lent our expertise, quality machinery and resource to move earth, realign and r...
Morrinsville Shared Path
December 10, 2023
September - November 2023
Nicholls and Uttinger Civil have completed the Matamata-Piako District Council's shared pathway project known as Morrinsville Rec Perimeter Path. The pathway project took place from September to November 2023 and was opened to the public on 10 December 2023.Our experienced r...
Studholme Street development
September 7, 2023
September - November 2023
Over ten weeks, Nicholls and Uttinger delivered three waters infrastructure and groundworks for the Studholme Street development for a private developer.We established three waters infrastructure for new residential lots, including connecting the lots onto a live wastewater ...